MEMPERCEPAT USIA PROYEK MENGGUNAKAN METODE PERT DAN CPM UNTUK PENGEMBANGAN SISTEM APLIKASI KOMPUTER
Abstract
At the time a development project application systems are often responsible for the project
constraints of time needed to complete the project itself, where the time is set based on the approximate
duration of each activity that must be done according to the plan changes from manejement. Based on
the problems, then a solution is required to determine the activities which can be complete. The
purpose of writing this journal is to provide a solution in overcoming the problems associated with the
acceleration time of a project application development system, while the purpose of writing this
journal is to apply methods of PERT and CPM in the age of speed or time required in completing a
project according to the age plan (UREN). Research methods that do the authors use the method of
study literature, and descriptive method by using the table-table operational variables. At the end of
the discussion of the results will be described how the age estimates (UPER) can be adjusted to the age
of the plan (UREN) long with a new activity, so that the responsible project can implement the project
in accordance with the target time is planned by management
Keys : PERT, CPM, UPER, UREN
Full Text:
PDFReferences
Heizer,Jay.& Barry Render, .2005. Manajemen
Operasi.,Jakarta: Salemba Empat.
Indriantoro, Nur dan Supomo Bambang. 2002,.
Metodologi Penelitian Bisnis untuk Akuntansi
dan Manajemen, Edisi pertama. Yogyakarta:
BPFE
Maharesi, Retno. 2002 . Penjadwalan Proyek
Dengan Menggabungkan Metode PERT dan
CPM. Depok: Universitas Gunadarma.
[Http:/repository.gunadarma.ac.id:8000/A51-
_Retno_Maharesi_154.pdf, Tgl akses
/07/2009 pukul 10:52]
Meridith J.R., Mantel SJ, Jr. 2002. Project
Management A Managerial Approach, Fourth
Editions. USA: John Willey & Sons, Inc
Purnama, Rachmat Adi. 1998. Manajemen Proyek.
Jakarta:AMIK BSI.
Rostianingsih, Silvia. 2006. Pembuatan Aplikasi
Manajemen Proyek Dalam Mengelola Proyek di
PT. X.. Depok:Universitas Gunadarma.
[http://repository.gunadarma.ac.id:8000/209//
Tgl akses 23/07/2009 pukul 09:42]
Schoeder, Roger. 2002. Manajemen Operas., Jakarta:
Erlangga.
Soeharto, Iman. 2002. Studi Kelayakan Proyek
Industri. Jakarta: Erlangga.
Subagyo, Pangestu. 2000. Dasar-dasar Operations
Research. Yogyakarta:BPFE.
Tubagus, Ali Haedar. 1997. Prinsip-prinsip Network
Planning. Jakarta:PT Gramedia.Yogyakarta:BPFE.
DOI: https://doi.org/10.31294/p.v11i3.4737
Copyright (c) 2009 Rachmat Adi Purnama
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
ISSN: 2579-3500